Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...


Name(Proposed) Explanation
1'IN_CONSTRUCTION'Works started on erection of the object expected to penetrate the obstacle collection surface in this location
2'COMPLETED'Works on erection of the object penetrating the obstacle collection surface in this location are completed and the construction equipment removed
3'DEMOLITION _PLANNED'Plans approved for demolition of the object penetrating the obstacle collection surface in this location
4'IN_DEMOLITION'Works started on demolition of the object penetrating the obstacle collection surface in this location
5'OTHER:PLANNED'Plans approved for the construction of the object at the given location. This status is not considered in performance calculation application.
6'OTHER'Any other status not listed above in following format 'OTHER:...STATUS...'

Coding example

To be added...

...